Fairview Park Playground Update

Excellent presentation given by the DCC Parks Dept on progress on the Fairview Park improvements project (including the playground).

Fairview Doc Updated Plan June 2010

The last page of the attached gives a schematic of the current preferred design.  Timeline looks like the following:

  • Request for tenders – July 2010
  • Tender assessment – August 2010
  • Contractor on-site – September 2010.

The funding for this project is already in place so we should see substantial progress by the end of 2010. Note that the playground going in is quite substantial – approximately twice the size of the play area installed in Maypark off the Malahide Road.